Architect Poul Ove Jensen designed the Samuel De Champlain Bridge as a cable-stay bridge to replace the original Champlain Bridge. The bridge hosts eight lanes for vehicles, and a central portion, still under construction, will accommodate light rail traffic. As the world’s widest two-plane cable-stay bridge, it ranks among the largest infrastructure projects in North America to date.
Durability drove every major design decision. Engineers incorporated stainless steel and high-performance concrete specifically to withstand corrosive environmental conditions and achieve a 125-year service life. One critical piece of this durability puzzle involved protecting post-tensioning strands from corrosion during installation. Winter grouting delays made this especially challenging, since these delays extend the window during which strands sit exposed to potential corrosion attack.
Post-tensioning strands carry enormous structural load on a cable-stay bridge this size. Protecting them from corrosion is therefore essential to reaching the project’s long service-life target. Once installed inside post-tension ducts, strands normally wait for grouting to complete their protection. Construction schedules, however, don’t always allow grouting to proceed on time.
Winter weather introduces a specific vulnerability here. Cold temperatures can push grouting operations back for extended periods. During this delay, strands remain exposed inside the ducts with no permanent protection in place. The longer this window stays open, the greater the risk that corrosion begins before grouting ever happens.
For a bridge engineered to last 125 years, even brief unprotected exposure during construction could undermine the durability goals behind the entire design. The team needed a temporary protection method that would hold up during this gap, without interfering with the grouting process once it finally moved forward.
The project team selected MCI®-309 to protect the post-tensioning tendons. Several practical advantages made this the optimal choice. Crews could fog MCI®-309 dry directly into the post-tension ducts, and the product required no flushing before grouting, which kept the overall workflow simple and efficient.
Before approving MCI®-309 for the project, the team needed to confirm one key requirement: the product could not interfere with the grouting bond between the tendons and the surrounding material. The team confirmed this quality well in advance, through corrosion and bond testing conducted at the grouting laboratory of Pennsylvania State University.
It applies as a dry fog. This method let crews treat post-tension ducts quickly, without introducing liquid that would need separate handling or removal.
It skips the flushing step. Because the product required no removal, it eliminated an entire process step across thousands of tendons, saving meaningful time at this scale.
It preserves the grouting bond. Laboratory testing at Pennsylvania State University verified this critical property before the product ever reached the job site, giving engineers confidence to specify it.
It bridges extended exposure windows. The product maintained protection through winter grouting delays that would otherwise have left strands vulnerable.
The post-tensioning team reported great satisfaction with the MCI®-309 application and used it for the entire duration of the project. Once the main structure reached completion, the team could point to a striking set of post-tensioning achievements:
The same project engineer now leads post-tensioning work on the Réseau Express Métropolitain light rail system and continues relying on MCI®-309 to protect post-tensioning strands on that project.
This project shows how rigorous laboratory testing can give engineers the confidence to specify a new protection method on a landmark infrastructure build. For engineers and contractors working on large bridge or post-tensioning projects, this case offers several practical lessons:
How do you protect post-tensioning strands from corrosion before grouting?
Fog a corrosion inhibitor, such as MCI®-309, directly into the post-tension ducts. This protects strands during the gap between installation and grouting, with no removal required.
Does MCI®-309 interfere with the bond between grout and tendons?
No. Corrosion and bond testing at Pennsylvania State University’s grouting laboratory confirmed MCI®-309 does not adversely affect the grouting bond.
Why do winter grouting delays raise corrosion risk?
Cold temperatures can push grouting operations back, which extends how long post-tensioning strands sit exposed inside ducts without permanent protection.
How much post-tensioning work did this project involve?
The project included 1,274 tons of post-tension strands, totaling 1,084 km (674 mi), along with more than 3,200 tendons stressed.