Cortec-Middle-East-logo-notaglineCortec-Middle-East-logo-notaglineCortec-Middle-East-logo-notaglineCortec-Middle-East-logo-notagline
  • ABOUT US
    • VpCI® Technology
    • MCI® Technology
    • The Cortec® Story
    • Engineering and Field Service
    • Cortec® R&D
    • Asset Integrity Assurance
  • INDUSTRIES
    • Oil & Gas
      • Aboveground Storage Tanks
      • Equipment Preservation
      • Hydrotesting and Mothballing
      • Mothballing
      • Cased Pipeline Crossings
      • Rig Stacking
    • Manufacturing Industries
    • Construction
      • Reinforced Concrete Structures
      • Post-Tensioned Structures
      • Concrete Repair
    • Power & Water
      • Above-ground Storage Tanks
      • Equipment Preservation
      • Hydrotesting and Mothballing
      • Mothballing
      • Cased Pipeline Crossings
    • Aviation
  • PRODUCTS
    • All Purpose Lubricant
    • Surface Preparation
    • Rust Preventives
    • VpCI® Powder
    • VpCI® Additives
    • VpCI® Packaging
    • VpCI® Emitters
    • MCI® for Concrete
  • CONTACT US
Home  »  case studies   »   Burj Khalifa
Published by Cortec Middle East on December 14, 2019
Categories
  • case studies
Tags
COVID-19's Effect on Large Buildings

Burj Khalifa

Protecting the Burj Khalifa Foundations for a 100-Year Service Life with MCI®-2005

Challenge

The Burj Khalifa needed a foundation that could last 100 years. The building sits on a concrete and steel podium with 192 piles. These piles descend more than 50 meters (164 feet). The foundations used 45,000 m³ of concrete and weigh more than 110,000 tonnes (121,254 US tons).

The groundwater around the site made the challenge harder. It contains more chloride than seawater, along with other contaminants. The project team needed extra protection for the substructure to reach its 100-year design life.

Background: Why Chloride-Rich Groundwater Threatens Foundations

Chlorides attack the steel inside concrete. Once they reach the rebar, they break down its natural protective layer. Corrosion then starts, and the steel expands. This expansion cracks the surrounding concrete from within.

Foundations face a special risk. Buried concrete stays in constant contact with groundwater, and no one can easily inspect or repair it later. Groundwater with more chloride than seawater makes this exposure even more severe.

A building of this size raises the stakes further. The foundation carries the entire structure, so any long-term damage would have serious consequences. For this reason, designers look for added layers of protection from the start.

Application

The team incorporated Cortec’s MCI®-2005 into the concrete mix design for the podium structure. This put corrosion protection inside the concrete, so it reached the embedded steel throughout the foundation.

Why MCI®-2005 Was Chosen

EMAAR Properties engaged GHD to review the proposed design. GHD also assessed the durability of the materials needed to provide the 100-year design life. After a thorough review of multiple technologies, the team chose MCI®-2005 as an additional layer of protection in the substructure. This part of the structure sits in harsh groundwater conditions.

It adds protection inside the concrete. As a Migrating Corrosion Inhibitor, MCI®-2005 works within the concrete to protect embedded rebar.

It suits large-scale concrete placement. Teams can add it to the mix design, which supports a project with 45,000 m³ of foundation concrete.

It earned independent review. An independent verification and testing authority reviewed the technologies before selection.

Conclusion

Cortec’s MCI®-2005 went into the concrete mix design for the podium structure to help achieve the 100-year service life. The Burj Khalifa’s construction used 330,000 m³ (431,500 yd³) of concrete and 55,000 tonnes (60,627 US tons) of steel rebar. Crews worked 22 million man-hours to complete it. The tower can hold up to 35,000 people at any one time, and it has a 100-year design life.

Why This Case Matters for Mega-Projects and High-Rise Developers

This project shows how developers can add corrosion protection to the foundations of a landmark tower. For engineers and owners planning large buildings in aggressive environments, this case offers several practical lessons:

  • Foundations need protection from day one — buried concrete is hard to inspect and repair later.
  • Groundwater chemistry matters — chloride levels higher than seawater call for extra protection.
  • Independent review adds confidence — GHD assessed multiple technologies before selection.
  • Design life drives specification — a 100-year target led to an added layer of protection.

Frequently Asked Questions

How do you protect foundation concrete from chloride-rich groundwater?
Add a migrating corrosion inhibitor, such as MCI®-2005, to the concrete mix. It protects embedded rebar as an extra layer of defense.

What design life did the Burj Khalifa target?
The Burj Khalifa has a 100-year design life.

How much concrete did the foundations use?
The foundations used 45,000 m³ of concrete and weigh more than 110,000 tonnes (121,254 US tons).

Who reviewed the durability of the materials?
EMAAR Properties engaged GHD to review the design and assess material durability for the 100-year design life.

Key Takeaways

  • The Burj Khalifa sits on a concrete and steel podium with 192 piles reaching more than 50 meters deep.
  • The groundwater contains more chloride than seawater, plus other contaminants.
  • The team added MCI®-2005 to the podium concrete mix as an extra layer of protection.
  • GHD reviewed multiple technologies before the team selected MCI®-2005.
  • The tower has a 100-year design life and can hold up to 35,000 people at a time.

Project Team

  • Concrete contractor: Unimix (Universal Concrete Products, LLC)
  • Architect: Skidmore, Owings & Merrill (SOM)
  • Independent verification and testing authority: GHD
  • Distributor: United Corrosion Technologies
  • Developer: EMAAR Properties
  • Construction manager: Turner

Cortec Products Used

  • MCI®-2005
Contact Us
Share
1
Cortec Middle East

Related posts

High Rise Building Restoration

High Rise Building Restoration

September 23, 2025

High Rise Building Restoration


Read more
Protection of Electrical Cabinets

Protection of Electrical Cabinets

September 23, 2025

Protection of Electrical Cabinets


Read more
Cleaning and Preservation of Spare Parts

Cleaning and Preservation of Spare Parts

August 24, 2025

Cleaning and Preservation of Spare Parts


Read more

Comments are closed.

Cortec Middle East-logo

QUICK LINKS

  • → HOME
  • → ABOUT US
  • → INDUSTRIES
  • → PRODUCTS
  • → CAREER
  • → CONTACT US
  • → PRIVACY
  • → MEDIA

REQUEST A WEBINAR

REQUEST NOW

SOCIAL MEDIA

ADDRESS

CORTEC® MIDDLE EAST,
2411 Tower B, Jafza One,
Jebel Ali Freezone, DUBAI,
UNITED ARAB EMIRATES


TEL. +971 4 434 0669
FAX. +971 4 434 0668
INQUIRIES@CORTEC-ME.COM

Copyright Cortec® Middle East.
All rights reserved. Cortec®, MCI®, VpCI® 126-Blue®, EcoFilm®, EcoWorks®, Rawn® and Bull Frog® are registered trademarks of Cortec® Corporation.
    • No translations available for this page

      REQUEST A FREE SAMPLE



        Download Layup Manuals

          Select Manual* :


          Offshore Rig Layup PR




            Layup of Land Based Drilling Rigs PR




              Request a Quote


                Talk To Our Experts


                  Subscribe Now

                    Apply Now

                      Upload Your CV