District cooling system preservation became essential at Abu Dhabi Reem Island when completed cooling plants needed to remain idle before the towers they would serve were ready.
Reem Island includes more than 100 towers, approximately 1.4 million m² of office space, and 850,000 m² of retail and community facilities. Four district cooling plants with capacities greater than 1,000 m³ were proposed for the development.
However, two plants were completed before their associated towers. Therefore, the end clients needed to mothball the completed facilities for up to two years.
During this period, the district cooling systems required reliable corrosion protection. In addition, the preservation strategy needed to minimize inspections, maintenance costs, and potential equipment replacement.
Completed district cooling systems can remain idle when surrounding developments face construction or commissioning delays.
During this period, internal metal surfaces require continued corrosion protection. Furthermore, the Reem Island systems included both ferrous and non-ferrous lines.
Therefore, an effective district cooling system preservation strategy needed to protect different metals while supporting a long mothballing period.
Wet lay-up provided a practical approach for maintaining the completed infrastructure until the associated towers were ready.
The project team proposed Cortec® VpCI® technology as an environmentally friendly and cost-effective preservation solution.
After reviewing the requirements, the client accepted VpCI®-649 BD for the wet lay-up program.
The team used a 0.4% dosage to achieve the required 24 months of corrosion protection.
In total, the project required approximately 2,970 gallons, equal to 164 drums, of VpCI®-649 BD.
As a result, the completed district cooling facilities could remain preserved while construction of the associated towers continued.
You can view the VpCI®-649 BD product information for additional product details.
The project required protection for up to two years. Therefore, the team adopted a wet lay-up strategy using VpCI®-649 BD.
The preservation approach provided corrosion protection throughout the district cooling system. Moreover, it protected both ferrous and non-ferrous lines.
Using a 0.4% dosage allowed the project to achieve the specified 24-month protection period.
Consequently, the district cooling system preservation program provided a practical way to manage completed infrastructure during the development delay.
Long-Term Protection
The client required up to 24 months of preservation. Therefore, the team selected VpCI®-649 BD for the extended mothballing period.
Ferrous and Non-Ferrous Protection
The district cooling system contained different metal types. The selected solution provided effective corrosion protection for both ferrous and non-ferrous lines.
Reduced Inspection Requirements
The wet lay-up preservation approach helped minimize inspection requirements during the idle period.
Cost-Effective Approach
The client wanted to reduce preservation, inspection, and potential replacement costs compared with the traditional methods considered for the project.
Environmentally Friendly Solution
The project team proposed Cortec® VpCI® technology to meet the requirement for an environmentally friendly and cost-effective preservation approach.
An effective district cooling system preservation program helps protect completed infrastructure when operation cannot begin immediately.
In this project, wet lay-up provided long-term protection for the cooling systems. In addition, the strategy addressed both ferrous and non-ferrous components.
The approach also helped minimize inspection requirements during the mothballing period. Therefore, the facility owners could maintain the completed systems until they were ready for operation.
Tabreed – Cooltech Energy adopted wet lay-up using Cortec® VpCI® technology for the Reem Island district cooling facilities.
The approach provided long-term protection against corrosion while helping minimize inspections, costs, and potential replacement requirements compared with the traditional methods considered.
Furthermore, the system protected both ferrous and non-ferrous lines.
As a result, the district cooling system preservation strategy provided a practical solution for protecting completed cooling infrastructure for up to 24 months.
What is district cooling system preservation?
District cooling system preservation protects idle cooling infrastructure against corrosion during mothballing, construction delays, or other periods before operation.
Why did the Reem Island cooling plants require preservation?
Two plants were completed before the towers they would support. Therefore, the end clients needed to mothball the facilities for up to two years.
Which product did the project use?
The project used VpCI®-649 BD.
What dosage of VpCI®-649 BD was used?
The team used a concentration of 0.4%.
How long did the preservation system provide protection?
The preservation strategy provided 24 months of protection.
How much VpCI®-649 BD did the project require?
The project required approximately 2,970 gallons, equivalent to 164 drums.
Did the system protect different metals?
Yes. The preservation approach provided corrosion protection for both ferrous and non-ferrous lines within the district cooling system.