Challenge The customer had procured two spare boiler tube bundles and faced a serious challenge in preventing the progress of corrosion during the outdoor storage of […]
Challenge Company had a huge inventory of unprotected equipment in their warehouse. The warehouse is located close to the sea resulting in the equipment rusting. The […]
Challenge One of the leading brands has fabricated 27 gas to liquid modules at Gulf Piping Company in Abu Dhabi for Escravos, Nigeria. After completion, the […]
Challenge The customer needed to prevent the progression of corrosion to the interior of 60 pipes during several years of storage, as a backup for the […]
Challenge A new Cortec® customer needed to store equipment for one year, on the deck of an offshore platform. Exposure to salt water spray, sand, and […]
Challenge The concrete foundations at PDO’s Runib Switchyard were experiencing visible cracking, spalling, and delamination. The structures were over twenty years old, with repairs made in […]
Challenge The project calls for the construction of a 57-storey serviced apartment tower with 320 units of 1, 2, 3 & 4 bedrooms located on Mohammed […]
Overview Alfardan mixed-use tower in the commercial area of Marina District, Lusail City encompasses a plot area of 12,541m². The overall design of the structure portrays […]
Overview The under-construction Al Majed Tower is a commercial tower in the Marina District of Lusail. It will comprise of 4 Basement + Ground + 25 […]